Hyndburn windfarm.
WTE were contracted to dismantle a fire-damaged turbine for Deutsche Windtechnik at Hyndburn windfarm; the first image shows the rotor being dismantled in February and the second shows the turbine being reinstalled in the first week of May. Our scope of work included cranes and mechanical services, blade disposal, tower reconditioning and full reinstall. The most challenging aspect was, of course, the preparation and dismantling works; these works were completed in a carefully managed manner within limited weather windows. Well done to all concerned.